| Location |
1068-2 Silcheon-ri, Hacheong-myeon,
Koeje-shi,
Kyeongsangnam-do, Korea (N34 58.79, E128 39.45) |
| Area |
9,279.30M2 |
| Numbers
of Cable Pans |
59 Pans (M : 32, S : 27) |
| Dimension
of Cable Tanks |
Dia. Inside 3m
Outside 10m
Height 5m |
Dimension
of Cable Pans
(Medium) |
Dia. Inside 3m
Outside 6m
Height 2.3m |
Dimension
of Cable Pans
(Small) |
Dia Inside 3m
Outside 6m
Height 1.8m |
| Cable Storage |
2,592.81 M2 (Width : 24.3M
Length : 106.7M) |
| Repeater
Storage |
234.00M2 (Width : 15.0M
Length : 15.6M) |
| Submersible
Eq, Storage |
540.00M2 (Width : 15.0M
Length : 36.0M) |
| Hand Cart
for Repeater/BU |
12 (for 9 Repeater and
3 BU) |
| Berthing
Capability |
Water Depth 8M
Length 120M |
Facilities
(Loading/Unloading etc.) |
1 Single Track Pair Linear
Cable Engine
(Max. Speed : 135m/min, Max. Tension : 25KN)
1 Cable Hauling Machine
(Max. Speed : 160m/min, Max. Tension : 30 KN)
Cable Through
Turn Sheave
Cable Tower
Note : Cable Pans, Hand cart for repeater/BU are existing
conditions. KT Submarine may provide more facilities as customer¡¯s
request. |
| Storage
Conditions |
KT Submarine depot which was constructed
on 14th August, 2000, and recently updated on the early
of August , 2001, store repeaters, BU, Shipboard RSE,
UJ consumables etc in air conditioned room to accommodate
technical requirement of each system as follows.
| Items |
Temperature |
| Cables |
-20¡É ~ +50¡É |
| Repeaters |
0¡É ~ +30¡É |
| BU |
0¡É ~ +30¡É |
|
| Extent
of work of the depot operators |
KT Submarine depot is designed
and constructed to provide suitable condition for the
cables, repeaters, BU, Shipboard test equipment, UJ piece
parts, etc. of Maintenance Authorities. Extent of work
of KT Submarine depot is as follows;
1) Appropriate storage facilities to provide proper
conditions for submersible plant
as described in each system technical specification.
2) Providing submersible plant transfer arrangement
from/to cableship to/from KT Submarine depot by KT Submarine whenever
customer request.
3) Insuring for the equipment, all cables and associated
plant stored.
4) Replenishment of spare submersible, if each MA requests.
|
| Responsibility
of depot operators |
Provide appropriate storage
conditions to use submersible plant in the maintenance
of each system as described in system technical specification,
as and when required. |